Methods of Cost Estimation in Projects - Tools and Techniques - The Constructor (2024)

🕑 Reading time: 1 minute

Reliable cost estimates are necessary for all projects. Without a cost estimate, it would be impossible to prepare a business plan, establish detailed budgets, predict resource requirement or control project costs.

In the process of cost estimation, the Project Cost Engineer uses either one or the combination of the following tools and technique:

Methods of Cost Estimation in Projects - Tools and Techniques - The Constructor (1)

Methods of Cost Estimation in Projects

  1. Expert Judgement
  2. Analogous Estimating
  3. Parametric Estimating
  4. Bottom-up Estimating
  5. Three-point Estimating
  6. Data Analysis (Alternative analysis/Reserve analysis)
  7. Project Management Information system
  8. Decision making (voting)

1) Expert Judgement Method

Expertise should be considered from individuals or groups with specialized knowledge or training in team and physical resource planning and estimating.

Expert judgment, guided by historical information, provides valuable insight about the environment and information from prior similar projects.

Expert judgment can also be used to determine whether to combine different methods of estimation and how to reconcile differences between them.

2) Analogous Estimating Method

Analogous cost estimating uses the values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measurement for a current project.

When estimating costs, this technique relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project.

It is most reliable when the previous projects are similar in fact and not just in appearance, and the project team members preparing the estimates have the needed expertise.

3) Parametric Estimating Method

Parametric estimating uses an algorithm or a statistical relationship between historical data and other variables (e.g., square footage in construction) to calculate resource quantities needed for an activity, based on historical data and project parameters.

For example, if an activity needs 4,000 hours of coding and it needs to finish it in 1 year, it will require two people to code (each doing 2,000 hours a year). This technique can produce higher levels of accuracy depending on the sophistication and underlying data built into the model.

4) Bottom-up Estimating Method

In the Bottom-up estimating method, team and physical resources are estimated at the activity level and then aggregated to develop the estimates for work packages, control accounts, and summary project levels.

Bottom-up estimating is a method of estimating a component of work. The cost of individual work packages or activities is estimated to the greatest level of specified detail. The detailed cost is then summarized or rolled up to higher levels for subsequent reporting and tracking purposes.

The cost and accuracy of bottom-up cost estimating are typically influenced by the size and complexity of the individual activity or work package.

5) Three-Point Estimating Method

The accuracy of single-point activity cost estimates may be improved by considering estimation uncertainty and risk and using three estimates to define an approximate range for an activity‘s cost:

• Most likely (M): The cost of the activity, based on realistic effort assessment for the required work and any predicted expenses.
• Optimistic (O): The activity cost based on analysis of the best-case scenario for the activity.
• Pessimistic (P): The activity cost based on analysis of the worst-case scenario for the activity.

Depending on the assumed distribution of values within the range of the three estimates the expected cost, cE, can be calculated using a formula. Two commonly used formulas are triangular and beta distributions. The formulas are:

  • Triangular Distribution
    E = (O+M+P)/3
  • Beta Distribution (from a traditional PERT analysis)
    E = (O+4M+P)/6

Cost estimates based on three points with an assumed distribution provide an expected cost and clarify the range of uncertainty around the expected cost.

6) Data Analysis Method

A data analysis technique used in this process includes but is not limited to alternatives analysis. Alternatives analysis is used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project. Alternatives analysis assists in providing the best solution to perform the project activities, within the defined constraints.

Instead of overestimating each cost, money is budgeted for dealing with unplanned but statistically predictable cost increases. Funds allocated for this purpose are calledcontingency reserves.

7) Project Management Information System Method

Project management information systems can include resource management software that can help plan, organize, and manage resource pools and develop resource estimates.

Depending on the sophistication of the software, resource breakdown structures, resource availability, resource rates, and various resource calendars can be designed to assist in optimizing resource utilization.

8) Decision-Making Method

Some decision techniques are unanimity, majority, plurality, points allocation, and dictatorship. For unanimity, everyone must agree; there is a shared consensus. A majority or plurality is usually determined by a vote. For a majority, the decision must be agreed to by more than half the participants.

Read More: Types of Construction Cost Estimation and Their Purposes
Top 10 Estimation Software in Construction Industry

Methods of Cost Estimation in Projects - Tools and Techniques - The Constructor (2024)

FAQs

What are the methods of cost estimation? ›

There are four principal cost estimating methodologies: 1) Comparison/analogy, 2)Parametric, 3) Detailed engineering/bottom up, and 4) Extrapolation from actual costs.

What are the techniques used in project cost estimating? ›

Cost estimation in project management is the process of forecasting the financial and other resources needed to complete a project within a defined scope. Cost estimation accounts for each element required for the project — from materials to labor — and calculates a total amount that determines a project's budget.

What are the types and methods used in estimating construction projects? ›

Estimating Methods. There are four primary methods used to estimate construction costs. Those methods are known as Project Comparison Estimating or Parametric Cost Estimating, Area & Volume Estimating, Assembly & System Estimating, and Unit Price & Schedule Estimating.

What are the methods of costing a project? ›

Answer: The most common costing methods are process costing, job costing, direct costing, and Throughput costing. Each of these approaches can be used in various production and decision-making situations.

What are the three basic types of cost estimating? ›

The three types of cost estimates are design, bid, and control estimates. Design estimates are prepared in the project preliminaries which gives the order of magnitude of the project cost. Bid estimates are used in the tendering phase of the project which details project overheads and other indirect costs.

Which tool is used to estimate cost? ›

Parametric estimating uses statistical modeling to develop a cost estimate. It uses historical data of key cost drivers to calculate an estimate for different parameters such as cost and duration. For example, square footage is used in some construction projects.

What is the most accurate cost estimating technique? ›

Breaking down projects into smaller tasks, a process known as work breakdown structure (WBS), is fundamental for improving the accuracy of cost estimates. This methodical deconstruction allows project managers to analyze each task individually, considering the specific resources, time, and labor required.

How to estimate construction costs? ›

What is the formula to calculate construction cost? To calculate the construction cost, you simply need to multiple your area value by the construction rate per square feet or square metre. The construction rate depends on various factors such as the plot's location, potential cost of labour and raw materials, etc.

What is the cost estimation process in construction? ›

In general, construction estimators follow a process that begins with reviewing bid documents, including construction specifications and contract documents, and includes steps to account for every known cost, including materials, labor, insurance, and overhead.

What is the costing method by construction? ›

Construction job costing is a detailed accounting method used to calculate track and assign expenses to specific projects and monitor budgets. Costs typically fall into one of three categories: labor, materials and overhead. Costs can be either direct or indirect. Construction job costing is inherently complex.

What are costing methods vs techniques? ›

Costing methods are the process of determining the costs of a product or service. With this concept, several methods are developed, to ascertain the pricing. These techniques analyse various cost components such as raw materials, labour, overhead expenses and many other significant factors.

What is the difference between costing methods and techniques? ›

Costing methods are use to ascertain the cost of product or services. For example- job costing, process costing, contract costing etc. While costing techniques are used to control and minimize the cost. Examples of costing techniques are -Activity Costing (ABC), Marginal Costing etc..

What are the two main methods of costing? ›

Job costing and process costing are the two basic methods of costing. Job costing is suitable to industries which manufacture or execute the work according to the specifications of the customers. Process costing is suitable to industries where production is continuous and the units produced are identical.

What is the most accurate method of estimating cost? ›

The most comprehensive and accurate method of cost estimating is the b-quantity survey method. This method involves breaking down a construction project into its individual components and estimating the quantities of materials, labor, and equipment required for each component.

Which is the most accurate cost estimation method? ›

Detailed estimate is the most accurate method and consist of working out the quantities of each of item of works and working the cost. The dimensions are taken directly from the drawings and quantities of each item are calculated.

Top Articles
Latest Posts
Article information

Author: Margart Wisoky

Last Updated:

Views: 6383

Rating: 4.8 / 5 (78 voted)

Reviews: 93% of readers found this page helpful

Author information

Name: Margart Wisoky

Birthday: 1993-05-13

Address: 2113 Abernathy Knoll, New Tamerafurt, CT 66893-2169

Phone: +25815234346805

Job: Central Developer

Hobby: Machining, Pottery, Rafting, Cosplaying, Jogging, Taekwondo, Scouting

Introduction: My name is Margart Wisoky, I am a gorgeous, shiny, successful, beautiful, adventurous, excited, pleasant person who loves writing and wants to share my knowledge and understanding with you.